Another commissioning of the reduction and measurement station is behind us!

On May 10, in Silesia, the technical acceptance of the Io reduction and measurement station with a capacity of 10,000 m3 / h was carried out, which will be one of the basic reduction stations supplying one of the largest cities in our voivodeship. 

The handover of the construction site took place on October 18, 2021, after which work began related to the construction of a temporary reduction and measurement station and the disassembly of the existing station. The ground works preparing for the construction of the target station were carried out in December and January, while the assembly of the technological part, the odorization plant and the I&C equipment began in February.

In the last week, all connections to the operator's gas network were made, which allowed, inter alia, to to start the technical acceptance.

There is still a final commissioning and commissioning of power ahead of us.